Showing posts with label Cost Management. Show all posts
Showing posts with label Cost Management. Show all posts

Wednesday, June 21, 2017

Metode Earned Value

Metode Earned Value (Pengukuran Kinerja)

Dalam penentuan kinerja proyek kita dapat menggunakan metode Earned Value atau Nilai Hasil, informasi yang ditampilkan berupa indicator dalam bentuk kuantitatif, yang menampilkan informasi dalam bentuk progress biaya dan jadwal proyek.
Indikator ini akan memberikan informasi posisi kemajuan proyek dalam jangka waktu tertentu serta dapat  memberikan indicator- indicator proyek.

Indikator- Indikator tersebut adalah:
1. BCWS (Budgeted Cost of Work Schedule), dalam hal ini menggambarkan anggaran rencana sampai dengan periode tertentu terhadap volume rencana proyek yang dikerjakan.
2. BCWP (Budgeted Cost of Work Performance), yaitu penggambaran anggaran rencana proyek pada periode tertentu terhadap apa yang telah dikerjakan pada volume pekerjaan aktual.
3. ACWP (Actual Cost of Work Performed) yaitu penggambaran anggaran aktual yang telah dihabiskan untuk pelaksanaan pekerjaan pada keadaan volume pekerjaan aktual.

Berbekal pada ketiga indicator diatas, maka pengukuran kinerja biaya dan waktu untuk metode Earned Value dengan menggunakan 3 jenis Kurva S sebagai nilai kumulatif biaya dengan fungsi waktu, yang tentunya terintegrasi dalam satu tampilan yang terdiri atas nilai kumulatif biaya:
BCWS, BCWP & ACWP.

Kemudian dilakukan analisis terhadap penyimpangan yang terjadi pada biaya dan waktu atau jadwal dengan cara melakukan pengukuran sebagaimana diuraikan dibawah ini:

1. Penyimpangan Jadwal / Waktu
    a. SV (Schedule Variance) = BCWP – BCWS. Bila SV > 0, maka progress actual > rencana, maka terjadi percepatan proyek. Bila SV < 0, maka terjadi keterlambatan proyek terhadap rencana (Schedule Over run).
    b. SPI (Schedule Performance Index) = BCWP / BCWS. Bila SPI > 1, maka progress actual > rencana, maka terjadi percepatan proyek terhadap rencana (Schedule under run). Bila SPI < 1 , maka progress actual < rencana, maka terjadi keterlambatan proyek terhadap rencana (Schedule Over run).
2. Penyimpangan Biaya
   a. CV (Cost Variance) = BCWP – ACWP. Bila CV > 0, maka biaya volume actual > biaya actual (Cost under run). Bila CV < 0, maka biaya volume actual < biaya actual (Cost over run).
   b. CPI (Cost Performance Index) = BCWP / ACWP. Bila CPI > 1, maka biaya volume actual > biaya actual (Cost under run). Bila CPI < 1, maka biaya volume actual < biaya actual (Cost Over run).

Dengan menghitung indeks- indeks seperti diatas akan terlihat bahwa proyek akan menjadi terlambat atau sebaliknya akan lebih cepat dan biaya yang harus dikeluarkan akan berlebih atau kurang dari yang telah dianggarkan, maka kemajuan proyek untuk waktu yang akan datang bisa diramalkan dengan cara seperti di bawah ini:

1. Perkiraan penyelesaian proyek (Estimated Completion Date). ECD = (Sisa waktu / SPI) + waktu terpakai. Persentase keterlambatan / percepatan = 100% - ECD / jadwal Rencana x 100%
2. Perkiraan Biaya Penyelesaian Proyek (Estimated at Completion). EAC = sisa anggaran / CPI + ACWP = (Total Biaya – BCWP)/CPI + ACWP. Persentase biaya penambahan/penurunan biaya actual terhadap anggaran biaya = 100% - EAC / Total biaya x 100%
3. Earned Value (Nilai Hasil) = BCWP (Biaya penyelesaian volume pekerjaan pada periode tertentu)

Monday, June 19, 2017

Determine Budget

1. Determine Project Budget

This process of aggregating the estimated costs of individual activities or work packages to establish an authorization cost baseline. This baseline includes all authorized budgets, but excludes management reserves.
The inputs, tools, techniques, and outputs of this process are describes below.












1.1 Determine Budget: Inputs 

The most important inputs to this process are the estimates determined in the previous process which is Cost Estimates. Other important inputs come from other knowledge areas such as Scope, Time, Human Resource, Risk and Procurement. This process requires the following inputs:

1.1.1 Cost Management Plan
This plan describes how the project costs will be managed and controlled

1.1.2 Scope Baseline
As described in the previous process which is Cost estimates, the scope baseline is a component of the project management plan and includes the product descriptions, acceptance criteria, key deliverables, project boundaries, assumptions, and constraints about the project.
It may also include requirements with contractual and legal implications for health, safety,security, performance, environmental, insurance, intellectual property rights, licenses and permits.

1.1.3 Activity Cost Estimates
These are outputs from the previous process which is Cost estimates

1.1.4 Basis of Estimates
Supporting detail for cost estimates should be specified as describes above. Any basic assumptions dealing with the inclusion or exclusion of indirect costs in the project budget are specified in the basis of estimates.


















1.1.5 Project Schedule
As described in the previous process which is cost estimates, the project schedule includes a planned start date and planned finish date for each activity as well the resources required This information can be used to aggregate costs to the calendar period in which the costs are planned to be incurred.

1.1.6 Resource Calendars
These provide information on which resources are assigned to the project and when they are assigned. This information can be used to indicate resource costs over the duration of the project.

1.1.7 Risk Register
This is an output of process Identify Risks and is used to aggregate costs for risk responses to obtain the contingency reserves for the project.

1.1.8 Agreements
This is an output of procurement management process and applicable contract information and costs relating to products, services, or results that have been purchased are included when determining the budget.

1.1.9 Organizational Process Assets
These are the processes or process related assets that can be used in this process including: Existing formal and informal cost budgeting related to policies, procedures and guidelines as well as cost budgeting tools and reporting methods.

1.2 Determine Budget: Tools and Techniques 
There are five tools and techniques that can be used:

1.2.1 Cost Aggregation
Cost estimates are aggregated by work packages in accordance with the W.B.S. The work package cost estimates are then aggregated for the higher components levels of the W.B.S (such as control accounts) and ultimately for the entire project.

1.2.2 Reserves Analysis
This can be establish both the contingency reserves and the management reserves for the project.
  1. Contingency reserves are allowance for unplanned but potentially required changes that can results from realized risks identified in the risk register.
  2. Management reserves are budgets reserved for unplanned changes to project scope and cost.
1.2.3 Expert Judgment
This expertise is provided by any group or individual with specialized knowledge or training and is available from many resources, including: other units within the organization, consultants, stakeholders, including customers or sponsors, professional and technical associations, industry groups, subject matter experts, and project management office (P.M.O).

1.2.4 Historical Relationships
This refer to using historical data from other projects in which costs are known for the same or similar activities.

1.2.5 Funding Limit Reconciliation
The expenditures of funds should be reconciled with any funding limits on the commitment of funds for the project. A variance between the funding limits and the planned expenditures will sometimes mean rescheduling the work to level out the rate of expenditures. This can be accomplished by placing imposed date constraints for work into the project schedule.

Cost aggregation of the work packages produces the cost estimate of the project. Adding the cost of risk responses and contingency reserves produces the cost baseline. Adding the management reserves, which are not controlled by the project manager but by management, to the cost baseline, provides the cost budget. If the funding for the whole project is incremental, then care must be taken to ensure that the project does not run out of money as a result of getting too far ahead of the schedule.


1.3 Determine Budget: Outputs 

This process will create the following outputs:



1.3.1 Cost Performance Baseline
This specifies what costs will be incurred and when. This matters because most projects will not receive their funding as a lump sum at the beginning but will be financed according to a monthly or quarterly budget. This means that the project manager will need to indicate when funds need to be available.

The simplest way to produce a cost baseline would be to aggregate all of the anticipated costs of the project and assume that they would be needed in proportion to the planned timescale.

For example:

Project Total cost was $ 100,000
Project Planned to take 20 weeks

Then a simple cost graph could be produced with the vertical axis calibrated in dollars and the horizontal axis calibrated in weeks.

You could produce a simple cost graph by assuming that the planned cost per day was linear, that is as a straight line coming from the origin to a point that is aligned to $ 100,000 on the vertical axis and 20 weeks on the horizontal axis as shown:


We have just created the cost performance baseline for that project as it takes the estimated project expenditures and align them with dates on the Calendar. This allows the organization to plan for cash flow and to make suitable arrangements in advance so that the funds are available when needed and not before.

This might be accurate enough for a very simple project where both the labor and material costs were fairly constant from day to day. But for projects with any degree of complexity it is necessary to produce separate cost baselines for different categories of expenditure, such as human resources at different labor rates, plant, materials and other equipment.




















For this reason the cost performance baseline may consist of several sub baselines, which can be aggregated to produce totals. In most projects the rate of expenditures is not linear but follows an "S" shaped curve as shown.

The reason for this is that the rate of spent at the beginning and end of the project is typically lower than that during the execution phase.

1.3.2 Project Funding Requirements

        These are derived from the cost baseline described above and need to reflect the cash flow needs of the project including management reserves and contingencies. They are an important output, because they may require the project schedule to be adjusted to the necessities of the periodic project funding requirements.

1.3.3 Project Document Updates
      This include the activity cost estimates, risk register and project schedule

Friday, June 16, 2017

Cost Control in Project

         Once the project starts, it's necessary to keep track of actual cost and committed cost so they can be compared to the CBC (Cumulative Budget Cost).

1. Actual Cost
    To keep track of actual cost on a project, it's necessary to set up a system to collect, on a regular and timely basis, data on funds actually expended. Such a system might include procedures and forms for gathering data. An accounting structure should be established based on the work breakdown structure numbering system so that each item of actual cost can be charged to the appropriate  work package. Each work package's actual cost can then be totaled and compared to it's CBC.
     Weekly time sheets are often used to collect actual labor costs. Individuals working on the project indicate the numbers of the work package on which they worked and the number of hours they spent of each work package.
    These hours are hours are then multiplied by the hourly cost rate for each individual to determine the actual dollar cost. In companies using a matrix organization structure, individuals may be assigned to several project concurrently. In such cases, the individual has to indicate the proper project number as well as the work package number on the time sheet to ensure that the actual labor costs are charger to the appropriate project. When invoices are received for materials or services that were purchased for use on the project, they, too have to be charged to the proper work package number.

2. Committed Cost


    In many projects, large dollar amounts are expended for materials or services that are used over a period longer than one cost reporting period. These committed costs need to be treated in a special way so that the system periodically assigns a portion of their total cost to actual cost, rather than waiting until the materials or services are finished to charge to the total actual costs.
    Committed costs are also known as commitments or encumbered costs. Costs are committed when an item (material, subcontractor) is ordered, usually by means of a purchase order, even though actual payment may take place at some later time when the material or service has been completed,  delivered, and invoiced. When a purchase order are committed and are no longer available to be spent on other project activities. The committed amount must be considered as encumbered, or set aside, because funds will be needed to pay the supplier or subcontractor at some time in the future, when the material or service is delivered and an invoice is received.
For example, if you hire a Contractor to paint your home for $ 5,000, you have committed $ 5,000, even though you may not actually pay the Contractor until the work is finished.
     To permit a realistic comparison of actual cost to cumulative budgeted cost, portions of the committed should be assigned to actual cost while the work being performed. In some case, the supplier or subcontractor may require progress payments, rather than waiting until all the work is finished before paid. In such situation, when an invoice is received from the supplier or subcontractor for a partial progress payment, the amount of that invoice should be charged to the actual cost for the proper work package.


3. Comparing Actual Cost to Budgeted Cost

     As data are collected on actual cost, including portions of any committed cost, they need to be totaled by work packages so that they can be compared to the cumulative budgeted cost.
Figure 1.0 shows actual cost by time period for each work package through week 8 (Packaging machine project). Also shown is the period by period actual cost for the entire project, as well as the cumulative actual cost (C.A.C).


















Figure 1.0 indicates that at the end of week 8, $ 68,000 has actually been expended on this project. The CBC in Figure 4.0 reveals that only $ 64,000 was budgeted to have spent by the end of week 8. There is a Variance of the $ 4,000 the project is over running its Budget.























Project Budgeting

            The Project budgeting process involves two steps. First, the project cost estimate is allocated to the various work packages in the project work breakdown structure. Second, the budget for each  work package is distributed  over the duration of the work package so that's possible to determine how much of its budget should have been spent at any point in time.

1. Allocating the Total Budgeted Cost
Allocating total project costs for the various elements, such as Labor, Materials and Subcontractors to the appropriate work packages in the work breakdown structure will establish a Total Budgeted Cost (T.B.C) for each work package. There are two approaches to establishing  the T.B.C for each work package. One is a top down approach , in which Total Project Cost (For labor, materials and so forth) are reviewed in relation to the work scope for each work package, and a proportion of the total project cost is allocated to each work package.
The other is a bottom up approach, which is based on an estimate of the costs for the detailed activities associated with each work package. The project costs is usually estimated when the proposal for the project is prepared, but detail plans are not usually prepared at this time. At the start of the project, however, detailed activities are defined and a network plan is developed. Once detailed activities have been defined, time, resource, and cost estimates can be made for each activity. The T.B.C for each work package will be the sum of the costs of all the activities that make up that work package.

Figure 1.0 illustrates the allocation of costs to individual work packages in the work breakdown structure for a $ 600,000 project. The amount allocated to each work package represents the T.B.C for completing all the activities associated with the work package. Whether the top down or the bottom up approach is used to establish the total budgeted cost for each work package, when the budgets for all the work packages are summed, they can not exceed the total project budgeted cost. 


Figure. 2.0 is  a network diagram for a project to make a specialized automated packaging machine and install it at the Customer's factory. The machine will insert the customer's product into boxes rolling by at high speed on conveyor. The project consists of three activities, and the network diagram shows the duration for each activity. 


Figure 3.0 shows the work breakdown structure with the total budgeted cost for each work package.

2. Developing the Cumulative Budgeted Cost


        Once a total budgeted cost has been established for each work package, the second step in the project budgeting process is to distribute each T.B.C over the duration of its work package. A cost is determined for each period, based on when the activities that make up the work package are scheduled to be performed. When T.B.C for each work package is spread out by time period, it can be determined how much of the budget should have been spent at any point in time. This amount is calculated by adding up the budgeted costs for each time period up to that point in time. This total amount, known as the Cumulative Budgeted Cost (CBC), is the amount that was budgeted to accomplish the work that was scheduled to be performed up to that point in time. The CBC is the baseline that will be used in analyzing the cost performance of the project.

        For the packaging machine , Figure 4.0 shows how the T.B.C for each work package is spread over the time periods,  based on the estimated durations shown in Figure 2.0, also shown is the period  by period  budgeted cost for the entire project, as well as its cumulative budgeted cost (CBC). Figure 4.0 indicates that $ 32,000 was budgeted to accomplish the work that was scheduled to be performed through week 5. The Period over which budgeted  costs are spread usually are determined by the earliest start and finish times for the activities in the baseline project schedule (adjusted to take into account resource leveling or resource limited scheduling)

With the CBC value's, its possible to draw a cumulative budgeted cost curve to illustrate budgeted expenditure over the duration of project. Figure 5.0 shows the cumulative budgeted cost curve for the packaging machine project. Although the table in Figure 4.0 and the cost curve in Figure 5.0 display cumulative budgeted cost for the total project, a similar table and curve can be made for each work package, if desired.


























            The CBC for the entire project or each work package provides a baseline against which actual cost and work performance can be compared at any time during the project. It would be misleading to merely compare actual amounts expended to the total budgeted cost for the project or work package, as cost performance will always look good as long as actual costs are below the T.B.C.

Friday, January 13, 2017

Cost Control Management

1. COST CONTROL

This is the process of monitoring the status of the project budget and managing changes to the cost baseline. It involves taking the cost baseline and performance data about what has actually done in order to determine the work accomplished against the amount spent.
Monitoring the expenditure of funds without regard to the value of work being accomplished for such expenditure has little value to the project other than to allow the project team to stay within the authorized funding. The key to effective cost control is the management of the approval cost performance baseline and the changes to that baseline.

For those projects that are funded at various stages and output this process are described below.














2.     COST CONTROL INPUT
2.1.  Project Management Plan

The project management plan described above contains the cost performance baseline, which can be compared with the actual results to determine if a change, corrective action or preventive action is necessary. It also contains the cost management plan that describes how the project costs will be managed and controlled.


2.2.  Project Funding Requirement
The cost baseline described above and need to reflect the cash flow needs of the project including management reserves and contingencies.

2.3.  Work Performance Information

This includes information about project and also includes costs that have been authorized and incurred, and estimates for completing project work.

2.4.  Organizational Process Assets

These include existing formal and informal cost control related policies, procedures and guidelines, cost control and the monitoring and reporting methods to be used.

2.5.  Cost Controls: Tools and Techniques

Earned Value Management (E.V.M), forecasting, the T.C.P.I (To Complete Performance Index), and performance reviews are the main techniques used, along with the project management software. Earned Value Management takes a snapshot of the present moment to see how the project is doing.
The techniques for forecasting and T.C.P.I shows how the future of the project will evolve given how the project is doing now. The performance reviews compare the past performance to see how the project has evolved up until the present moment.



Reserve analysis takes into account the extra layers on top of the cost estimates, the contingency reserves (which are added to the cost estimates to get the cost baseline) and the management reserves (which are added to the cost baseline to get the project budget). It should be decided whether any unused reserves are going to be left in the project budget, or whether they will be taken out.

2.6.  Earned Value Management (EVM)
It is defined as follows:
Earned Value Management (EVM) is a methodology that combines scope, schedule and resource measurements to assess project performance and progress . It is a commonly used method of performance measurement for projects. It integrates the scope baseline with the cost baseline, along with the schedule baseline, to form the performance baseline, which helps the project management team assess and measure project performance and progress.
It is a project management technique that requires the formation of an integrated baseline against which performance can be measured for the duration of the project.


The Earned Value compares the money spent ($130 K) with what should have been spent ($150 K). This means that:
      Work to the notional value of $140 K has been done but, $130 K has actually been spent. There fore the project is $10 K under its planned cost at this point.
Also the project has only completed $140 K of work as opposed to the $150 K that was planned.

       This means that the project is $10 K behind schedule.

It may seem strange to express time in dollars but the reason it makes sense is because time is money.

2.7.  Forecasting
As the project progresses, the project team can develop a forecast for the estimate at completion that may differ from the budget at completion costs. The most common approach is a manual, bottom up summation by the project manager and project team.

2.8 To Complete Performance Index (TCPI)
This is an earned value term which describes the performance needed for you to achieve your earned value targets, and hence to control cost.


2.9 Performance Reviews
These compare cost performance over time, schedule activities or work packages over running the budget, and estimated funds needed to complete work in progress. They are used to determine those areas where costs are under or over performing, and yet again uses earned value management to compare actual results with the cost baseline and hence the ability to be able to control cost via forecast trends and indexes. 

2.10 Reserve Analysis
Monitors the status of contingency reserves and management reserves. Unused contingency reserves for probable risk events that do not occur may be removed from the project budget.

3. Cost Controls: Outputs
This process will create the following outputs:

3.1 Work Performance Information
It is important to capture all of the relevant costs when measuring progress. This information should be communicated to the project team and concerned stakeholders on a regular basis.


3.2 Cost Forecast
These determine the extra funding that will be required based on the actual costs accrued so far. Earned Value can help forecast not just remaining costs but also the required total cost for the project. This information should be communicated to the project team and concerned stakeholders on a regular basis.

3.3 Change Requests
These refer to cost related change request of course, may be needed if the control cost process shows that the project will be costing more or less than the cost baseline. In this case it changes will be needed to bring the project back on track.


3.4 Project Management Plan Updates
This relates to any changes such as those to the cost baseline or the cost management plan. It may also relate to other aspects of the project management plan for example a modification to project scope.


3.5 Project Document Updates
These include cost estimates and are normally needed as a consequence of project plan updates.


3.6 Organizational Process Assets Updates
These include, causes of variances, corrective action chosen and other types of lessons learned from project cost control in order to improve control cost management in the future projects. If either the work performance information or the cost forecasts indicate that there is a variance in either the cost or schedule performance of the project that needs correcting, then a change request may be recommended.

  • Corrective action aims to reduce the variance
  • Preventive action aims to prevent the variance from growing larger in the future.
It may happen, however, that the variance is so large that the cost baseline is determined to be unrealistic, in which case it may be suggested that the cost baseline itself is changed.
In any case, these change requests are outputs of this process, but then are inputs to the process in the integration management knowledge are called process Perform Integrated Change Control.

Thursday, December 15, 2016

Change Order in Project



1.0 MANAGING CHANGES IN THE PROJECT

During the course of a project, circumstances may come to light that necessitate minor or major adjustments to the plan. Not all changes are bad, yet not all changes can be made once a project is underway and project time, cost, and scope have been established.

Frequent scope changes may be an indication of inadequate up-front planning. They most often occur because of errors or omissions in the planning stage. Frequent changes may also be an indication of weak management in the organization, or a sign that the organization is trying to accomplish more work than available resources can handle. Changes may also be brought on by external events, such as changes in government regulations, new technologies, or new products or competitors.

It is important to establish a formal change control process to handle proposed changes to the plan. The system should include processes for submitting, evaluating, approving, and communicating changes in the project plan.
However, avoid making the system more complex than it needs to be. A lack of control can mean chaos, whereas an excessive amount of red tape can be overly burdensome to the project. Large projects with high visibility or a great degree of risk deserve a more rigorous change control process.

Change control is necessary to manage the potential effects on the project budget, schedule, and scope. Remember that the project triangle must be kept in balance. Changes in the time, cost, or scope of the project must be accompanied by appropriate changes in at least one other side of the triangle.
After the project is under way, the project sponsor may decide he wants new features added to the product, but he may still expect it to come in on the original schedule and budget. Change control can protect the project from “scope creep” (the tendency for scope to increase during the course of the project without proportionate increases in time or cost).

2.0 Actions
Consider the following actions to manage project changes:
  1. Establish processes for submitting, evaluating, approving, and communicating changes in the project plan, including changes in time, cost, or scope.
  2. Define tolerance guidelines within the approved project objectives so team members know which minor changes they can accept and which changes must go through the formal change control process.
  3. Review change requests with the project team. Consider the impact of the change on all aspects of the project. Determine what added value the change represents for the project sponsor, customer, or project team. Identify the causes of the change and determine if these causes necessitate changes in other areas of the project or in future projects.
  4.  Study alternative courses of action and determine their effect on the project.
  5. Submit change requests to the project sponsor or customer and receive the appropriate approval or rejection. Communicate approved changes to all concerned. Document and track all changes, reporting on their effect on the project.
3.0 Change Request and Approval Form
The form in Figure.1 illustrates the kind of information needed to control change requests. Develop an appropriate form to use with your project.

Figure.1
 
4.0 Change Control Log
A change control log (see Figure.2) also may be used by the project manager to document and track changes.
Figure.2


5.0 Such a form helps:
  1.  Keep track of changes.
  2.  Determine why changes are made.
  3. Justify changes to management.
  4. Capture lessons learned for future projects.
  5. For larger projects, you may want to hold a formal kickoff meeting with the project sponsor, customers, project team members, and other stakeholders to explain the roles and responsibilities of everyone present and communicate the project plans clearly and concisely.
  6. Be sure to communicate the appropriate level of project information to each group. Management may be interested in summary-level information, whereas team members need much more detail.
  7. Project management is the process of comparing actual performance to the plan to determine the variances, evaluate possible alternatives, and take appropriate corrective action. The ability to manage a project is directly tied to the effectiveness of the project plan. You need a plan to indicate where you are supposed to be, and you need status information to track where you are.


6.0 The steps in establishing a plan to monitor and manage a project are as follows:
  1. Determine information needs (what must be known to manage the project).
  2. Determine the methods to collect data (such as electronic, manual, on-site inspections, one-on-one interviews, or team meetings).
  3. Determine how frequently data must be collected (based on the length and requirements of the activity and your level of confidence in it). 
    Once project work begins, the project manager systematically collects status information and compares it with the schedule, budgets, and scope identified in the project plan to determine variances.
Not all variances have a negative impact on the project, and not all variances deserve corrective action.
    The project manager develops and analyzes solutions to the problem, then takes the appropriate corrective course of action.
Time management is the process of comparing actual schedule performance to the baseline schedule, in order to determine variances, evaluate possible alternatives, and take the appropriate action. Cost management is the process of comparing actual expenditures to the baseline cost plans, in order to determine variances, evaluate possible alternatives, and take appropriate action.
    Scope and quality management is the process of comparing actual performance to the scope statement, in order to determine variances, evaluate possible alternatives, and take the appropriate action. Resource management is the process of comparing actual performance to the resource plans, in order to determine variances, evaluate possible alternatives, and take the appropriate action.
     Some projects can be more tightly managed than others. Work that can be measured accurately can be managed with tighter tolerances. Work that is less precise (such as research or knowledge work) must be allowed greater tolerances.
Helpful tools to use in managing project objectives include inspections, statistical sampling, flow charting, control charts, trend analysis, Pareto diagrams, cause-and-effect diagrams, and earned value analysis.
Earned value analysis involves various calculations that measure and evaluate project performance by comparing the amount of work planned with what is actually accomplished.

         Establish a formal change control process to handle proposed changes to the plan while the project is in process. The system should include processes for submitting, evaluating, approving, and communicating changes in the project plan. Change control is necessary to manage the potential effects on the project budget, schedule, and scope.