Scheduling Overview
To effectively plan and control a project, the project
manager need to be able to process large amount of data quickly and accurately
to ascertain the complexity of the resulting schedule. The activity network and
the activity scheduled bar chart/GANTT chart are two of the key scheduling
steps, which are central to successful time management planning, cost
management and resource management planning. From the activity network, a
structure is created to allow for project control and tracking including
monitoring project progress, earned value management, information processing
and project reporting.
The activity network and the GANTT chart provide a highly
structured and methodical approach to project scheduling. Along with the
project resource loading chart and cost requirements, they are fundamental to
establishing the project baseline plan.
The scheduling steps continue from the project planning
definitions given by the work breakdown structure (WBS) and the duration/cost
estimations of work packages.
The major steps are:
1 .
Define
the relationships between activities
2 .
Draw
the activity network diagram
3 .
Perform
the network analysis
4 .
Transcribe
network analysis results to a GANTT Chart
5 .
Introduce
project “must dates”
6 .
Optimize
the activity network and resulting GANTT chart
7 .
Build
the cumulative cost estimate curve
8 .
Establish
and adapt the project’s resource requirements
With the advent of the project management software, there is
a strong temptation to build the strong temptation to build the activity
relationships and the network directly on the computer. The project manager
must persuade the team members to avoid this, as not only is it extremely
difficult to perform the precedence analysis on a computer screen, where few
activities can actually be seen and the whole network be visualized, it most of
all defeats all team dynamics objectives, as there is little or no active team
member collaboration, participation, and eventual ownership. Use “brain ware”
and “team ware” first, then use software.
Activity Networks
The first step before drawing the activity network is to
determine the logical and physical dependencies of the work packages. Only
activities are considered and ordered following a precedence analysis. The project
manager and the team members will thus convert the hierarchal WBS to a
sequenced network of activities. A network is not cyclical---there no loops, as
every task must be connected to another task or event, thus creating paths over
time.
The network is created based on assumptions about resource
availability and estimated durations of each task, as well as on the evaluation
of the interdependencies of work packages.
Determining the
sequence of work packages
The convention in building a network of activities is to have
a start activity at the beginning and finish at the end. Another convention is
to show the flow of the network from the left to right and not top to bottom.
Dependencies among work packages are defined and recorded for each. When the
predecessors are identified for each work package, they should only be for
immediate predecessors for a given work packages are possible and often exist.
Other than the start and finish, all work packages will have
a predecessor and successor work package. The network must also include all
dependencies and relationships to work package or events from and to external
interrelated and concomitant projects.
The project manager must recognize:
1. Mandatory
(physical) dependenciesà those dependencies that are inherent to the type of work
being done. They cannot and will not change, no matter how many individuals are
working on a task or how many hours are allocated to task.
2. Discretionary
(logical) dependenciesà those dependencies that are defined by the project team,
that offer the choice to the project manager to schedule tasks in a certain
way.
3. External
dependenciesà outside the realm of the project or outside the control of
the project manager, these dependencies may direct how portions of the project
schedule must be defined.
Building the precedence
chart of activities
Team work, the project manager and the core team will
construct and visualize the activity network on a wall, using post is notes
either taken from previous WBS structure or specifically developed for this
step.
The activity network can then be illustrated either as an
activity on arrow (AOA) or an activity on node (AON).
The activity on node
network
The activity on node (AON), also called the precedence
diagramming method (PDM), represents activities as the nodes, usually in the
shape of a rectangle and the dependencies as arrows.
This type of activity network offers a variety of relationships
that are discussed in the next section
Types of activity
relationships
It is essential to establish the most effective physical and
logical relationships for activities within the project’s network, as well as
to correctly define the interfaces from and to other projects. Only with a
solid structure and framework can the activity network subsequently reflect the
calendar for the project and its required resources.
The AON/PDM is very powerful, in that it offers four types of
relationships that allow for more flexibility in defining the precedence
between activities. Furthermore, the AON/PDM allows for meaningful ways to
accelerate or delay the schedule, as will be seen in section Lags and Leads.
There are four relationships, sometimes called constraints,
which are explained further in the following sections:
1.
Finish
to Start – FS
2.
Start
to Start – SS
3.
Finish
to Finish – FF
4.
Start
to Finish - SF
There is an additional relationships, a hammock, which also
explained below:
Finish to start relationships
The finish to start (FS) is the most common relationship. An
activity can only start if the preceding activity has been totally completed.
This relationship can be further developed by applying a delay between the two
activities by use of a lag.
Start to start relationships
The start to start (SS) represents the relationship between
the start dates of two activities. Precedence still exists between the two
activities and the direction of the relationship is important, as the start of
the successor activity is conditional only upon the start of the predecessor
activity. During project implementation, any delay on the start of the
predecessor will impact the start of the successor.
Finish to finish relationships
The finish to finish (FF) represents the relationship between
the end dates of two activities. Precedence still exists between the two
activities, and the direction of the relationship is important, as the end of
the predecessor activity. During project implementation, any delay on the end
of the predecessor will impact the end of the successor.
Hammock relationships
This is not a relationship per se. An extra activity, called
a hammock activity, is introduced in the network to group a number of activities
under one summary activity. It is often used to insert a higher level key
highlight for faster and easier reporting to senior management, who only wish
to capture the project’s important issues in the schedule at summary level.
Lag and Leads
Lags and Leads are techniques to introduce
duration delays or accelerations in the network. These are used for all types
of relationships.
No comments:
Post a Comment