Lag and Leads
Lags and leads are techniques to introduce duration delays or
accelerations in the network. These are used for all types of relationships,
the logic of predecessor/successor is respected; however the start and end date
calculations for each activity are adjusted according to the technique used
(Forward and Backward Passes).
Lags will delay the successor’s start or end date (depending
on the type of relationship, it has with its predecessor). Lags are often used
when the successor activity, in order to commence, requires the predecessor
activity to perform of its own work. At other times, the successor activity can
only be completed after receiving and utilizing the results of its predecessor.
Often lags are introduced in the network to cater for a lapse of time that does
not use resources.
Leads will accelerate the start date of the successor
activity. They are only used for FS links when seeking to optimize and fast
track the project.
Figure 1.0 the application of lags and leads
Forward and Backward Passes
The activity network represents the logical flow of work to
be performed. A completed and verified network illustrates the sequences of
activities. These sequences are called path. All the paths radiate from the
start point of the network and converge back into the end point.
Now it is time for the activity network to return meaningful
scheduling dates for each activity to the team. The critical path method (CPM)
provides for this. The method was developed in the 1950s in a joint venture
between Du Pont Corporation and Remington Rand Corporation. While the
scheduling method was developed specifically for the construction industry, it
can be applied to any project with interdependent activities. CPM enables the
project critical path to be determined by tracing the logical sequence of
activities that directly affect the completion date of the project through a
project network from start to finish. There may be more than one critical path
depending on workflow logic. A delay to progress of any activity on the
critical path will cause the overall project duration to be extended.
Using CPM, date calculations are made for each activity a
long each path by proceeding by a Forward pass of the network and then a
Backward pass (see Figure 2.0).
Figure 2.0
Each activity is then boxed by the following:
1.
Earliest
Start time – ES is the earliest time at which the activity can start depending
on its precedent activities.
2.
Earliest
Finish time – EF is the earliest time at which the activity can finish. This is
equal to the earliest start time for the activity plus the duration of the
activity.
3.
Latest
Start time – LS is the latest time at which the activity can start. This is
equal to the latest finish time for the activity minus the duration of the
activity.
4.
Latest
Finish time – LF is the latest time at which the activity can be completed
without delaying the project.
At this stage of scheduling it is important to note that all
calculations will be made in absolute terms of duration in the established
working unit, where the network’s start is set to zero.
The GANTT chart, once adopt to both civil and corporate
calendars, will present the schedule against a meaningful calendar.
Forward Pass
The forward pass is the technique used to calculate the
earliest start (ES) and earliest finish (EF) dates for each activity on each
activity on each path of the network. It is a relatively simple process,
requiring easy arithmetic (unless using PERT or other probabilistic estimating
technique). The principle for single predecessor, finish to start (FS)
relationships is straight forward:
The network start activity, of a duration of zero, is set to
zero. Its ES and EF are also set to zero. Proceeding down each path, the ES of
an activity is set to equal the EF of the predecessor activity. The EF of the
said activity is set to its ES plus its duration.
This process is followed until all ES and EF dates of all
activities are determined for all paths. As all paths converge to the finish
activity, which has a duration of zero, the ES of the finish can be set and its
EF set equal for the ES (see Figure 3.0).
Figure 3.0
Multiple Predecessor
When more than one predecessor exist, the ES of the activity
will be set to highest EF value of its predecessor.
In the example (see Figure 4.0), the paint walls activity
cannot start before both activities clean/dry walls an earliest finish (EF)
date of 15 and paint delivery with an EF dates, the resulting ES date of paint
walls become 36.
Figure 4.0
Backward pass
The backward pass is the technique to calculate the latest
start (LS) and latest finish (LF) dates for each activity on each path of the
network. It is a relatively simple process, requiring easy arithmetic.
The principle for single predecessor, finish to start
relationships is straight forward:
The pass commences with the network’s finish activity date.
The ES date of the finish activity has been calculated by the forward pass.
Since the activity has a duration of zero, then its EF date is set equal to the
ES. The LS and LF dates also set to equal the activity’s ES and EF.
Proceeding backwards along each path, the LF of an activity
is set to equal the LS of the successor activity. The LS of the activity is set
to its LF minus its duration. This
process is followed until all LS and LF dates of all activities are determined
for all paths. As all paths converge back to the beginning of the network, the
LF of the start activity can be set and the LS is set equal to it (see figure
5.0).
Figure 5.0
Calculating Float
(Slack)
Float is the amount of time that an activity can be delayed
past its ES or EF without causing a delay to:
1.
Project
completion date – Total Float (TF)
2.
Subsequent
activities – Free Float (FF)
Total Float
The Total float for an activity is the total amount of time
that a schedule activity may be delayed from its EF date without delaying the
project finish date, or violating a schedule constraint.
TF = LF – EF or LS - ES
Free Float
The Free float is the amount of time that an activity can be
delayed without delaying the ES of any immediate successor activity.
The Free float is determined between two
consecutive and is the difference between the successor’s ES start and the
predecessor’s EF.
Interesting Article. Hoping that you will continue posting an article having a useful information. Construction Project leads
ReplyDelete